Al Haer ISTP (BOOT)
Client: Saudi Water Partnership Company (SWPC)
Term: 25 years
Financial Close: February 2025
Scope:
- STP Capacity: 200,000 m3/day
- TSE Special Facilities: 400,000 m3/day
- TSE Pipeline: 32 km
Project Status: Active


Ras Tanura IWWTP (BOOT)
Client: Saudi Aramco
Term: 25 years (extendable 5 years)
Financial close: March 2024
Scope:
- IWWTP Capacity: 20,000 m3/day
- Wet Air Oxidation Unit
- Transmission Lines: 21 km
Project Status: Active


O&M and FM services for Wet Utilities at King Salman Energy Park (SPARK)
Client: ECOC/SPARK
Term: 3+2 years
Commencement: June 2023
Network Length:
- PW: 91.5 km
- Irrigation: 46 km
- Sewage: 58 km
Project Status: Active


Long Term O&M, STPs (ROT)
Client: National Water Company (NWC)
Term: 10 years
Commencement Date: May 2023
STP Capacity: 500,000 m3/day
- Hadda-1 STP Capacity: 125,000 m3/day
- Hadda-2 STP Capacity: 125,000 m3/day
- Arana-1 STP Capacity: 250,000 m3/day
Project Status: Active
Management, Operations and Maintenance (MOM) East Cluster
Client: National Water Company (NWC)
Population served: 5,270,000
Term: 7 years
Commencement date: April 2022
Cluster Features:
- Networks: 14,416 km
- Potable Water Plants: 66
- Treatment Plants: 27
- Boreholes: 1092
Project Status: Active


Jazan Economic City STP (O&M)
Client: Power and Utility Company for Jubail and Yanbu (Marafiq)
Term: 3+2 years
STP Capacity: 40,000 m3/day
Commencement Date: Q1 2022
Project Status: Active


Manfouha STP (O&M)
Client: Thabat Construction Company
Term: 3 years
STP Capacity: 200,000 m3/day
Commencement Date: September 2021
Project Status: Successfully colsed
Management, Operations and Maintenance (MOM) Northwest Cluster
Client: National Water Company (NWC)
Term: 7 years
Population Served: 3,100,000
Commencement Date: April 2021
Cluster Features:
- Networks: 15,000 km
- Potable Water Plants: 50
- Treatment Plants: 10
- Boreholes: 622
Project Status: Active


Dammam Industrial City-3 (O&M)
Client: Saudi Authority for Industrial Cities and Technology Zones (MODON)
Customers: 250+ (operations/under implementation)
Term: 2 years (annually renewed)
Commencment Date: March 2019
Potable Water: 6,000 m3/day
Project Status: Active


Hadda and Arana STPs (O&M) Re-awarded
Client: National Water Company (NWC)
Term: 3 + 1.5 years
Commencement Date: December 2018
STP Capacity: 500,000 m3 /day (peak 750,000 m3 /day)
- Hadda-1 STP: 125,000 m3/day
- Hadda-2 STP: 125,000 m3/day
- Arana-1 STP: 250,000 m3/day
TSE Channel: 90,000 m
Project Status: Successful closure into the long-term contract (May 2023)


King Khalid International Airport (KKIA) Potable Water Plant (BOT)
Client: General Authority for Civil Aviation (GACA)
Investment: SAR 300+ Million
Term: 28 years
Production:
- Potable Water: 25,000 m3/day
- Networks: 35 km
- Potable Water Reservoirs: 75,000 m3
- Raw Water Reservoirs: 25,000 m3
Project Status: Active


Hadda and Arana STPs (O&M)
Client: National Water Company (NWC)
Term: 2.5 years
STP Capacity: 500,000 m/day (peak 750,000 m3/day)
- Hadda-1 STP: 125,000 m3/day
- Hadda-2 STP: 125,000 m3/day
- Arana-1 STP: 250,000 m3/day
TSE Channel: 90,000 m
Project Status: Successfully closed


Leakage Detection and Water Management of Riyadh Water Network
Client: National Water Company (NWC)
Term: 4 years
Water Management:
- Distribution Zones: 29
- Leakage Detection to Achieve: <=12%
- Survey Works and Reports
- Initial and Final Loss Calculation
Project Status: Closed


Jeddah Water Management, City Wide
Client: National Water Company (NWC)
Term: 9 years
City Management JV Contract
- City Inhabitants: ~5 Million
- STP Capacity: 500,000+ m3/day
- Water Network: 5,000+ km
- Wastewater Network: 2,500+ km
Project Status: Closed


Dammam-I,II & Al Ahsa-I Industrial Cities Concession (ROT/BOT)
Client: Saudi Authority for Industrial Cities and Technology Zones (MODON)
Investment: ~SAR 500 Million
Customers: 1000+
Term: 30 years
- STP Capacity: 41,500 m3/day
- Industrial Water: 15,000 m3/day
- Potable Water: 47,800 m3/day
- Networks: 336,400+ km
Project Status: Active


Jeddah-I Industrial City Concession (BOOT)
Client: Saudi Authority for Industrial Cities and Technology Zones (MODON)
Investment: ~SAR 250 Million
Customers: 850+
Term: 20 years
- STP Capacity: 30,000 m3/day
- Industrial Water: 9,000 m3/day
- Networks: 143 km
Project Status: Active